As a follow up to Principal Roche’s email sent May 2nd, please be advised roof and tuck-pointing work started on Monday, May 6. Please take extra time and caution when walking on the narrow Marshfield sidewalk. This basic, critical work is necessary to prevent future leaks and ensure safety.

      1. Daily 4pm-9pm (only day work is scaffolding construction on May 6-7).

      2. After students’ last day (6/20), work will be all day 6am-3pm starting 6/21.

      3. Almost all work is external.

      4. Marshfield sidewalk will be scaffolded to half its width.

      5. Parking lot between playground and school will be scaffolded and unavailable until August. At least eight parking spaces will be used.  A wide path will remain for student access to the playground.

      6. On 6/21, all of parking lot will be dedicated to construction and unavailable to school personnel.

      7. All entrances and exits will still be available except possibly the north alley exit where construction staging may exist.

      8. Target completion date is August 9.

Thank you!

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s